Skip to main content

Project

Centre Park Link Bridge,
Warrington

C1536 290120 089

It takes a lot of expertise, teamwork and steel to build a new cross-river bridge for the famous Mersey, but that’s exactly what our team did.

Location
Warrington
Client
Warrington Borough Council
Main Contractor
Balfour Beatty
Engineer
Ramboll
Tonnage
200

We were appointed to supply, fabricate, paint, transport and erect the structural steelwork for the Centre Park Link bridge in Warrington.

C1536 290120 059

To meet this brief, the huge steel bridge sections were delivered to the site in nine separate braced pairs and were unloaded and assembled onto temporary trestles to form three sets of braced pairs. It took the use of a 150-tonne mobile crane for this operation.

C1536 290120 036

An LG1550 strut crane was mobilised to install the three assembled braced pairs, and, due to the tight site constraints, getting the crane on site required a huge amount of planning. It was closely coordinated to arrive on site and assembled in time for the installation of the bridge to commence. Delivery of the crane, and all its super-lift components, required the assistance of 12 support wagons that came on to the site in a planned sequence.

C1536 290120 144 INTERNAL USE ONLY

Each of the 45-metre long sections weighed 65 tonnes; once assembled, they were transported to the LG1550 crane for installation using ‘Self-Propelled Modular Transport’ (SMPT) units.

C1536 290120 017

The ground conditions were in our favour on this project and road closures (which can usually be required for projects of this magnitude), were not necessary as the access roads had not yet been constructed.

C1536 290120 031

Erection of the three bridge sections was successfully completed over the course of just two days. Now, there’s a shining example of our teams’ excellent work spanning the majestic Mersey.

C1536 290120 089